§ 27-150. Inspections to ensure plan compliance during construction.  


Latest version.
  • (a)

    Periodic inspections during construction of a stormwater management system shall be conducted by the city engineer, or conducted and certified by a professional engineer who has been approved by the city engineer. All inspections shall be at the sole cost of the permittee. The approved final stormwater management plan shall be used for determining compliance during construction inspections.

    (b)

    All inspections shall be documented with written reports that contain the following information:

    (1)

    The date and location of the inspection;

    (2)

    The name and qualifications of the inspector;

    (3)

    The specific components of the stormwater management system inspected;

    (4)

    Whether construction of the a stormwater management system was determined to be in compliance with the approved final stormwater management plan;

    (5)

    Any variations in the construction from the approved final stormwater management plan; and

    (6)

    Any other variations or violations of the requirements or conditions of the approved final stormwater management plan.

    (c)

    If the inspection is conducted by a professional engineer approved by the city engineer, the written report shall be submitted to the city engineer immediately upon completion of the inspection.

    (d)

    If any variations or violations are found, the permittee shall be notified in writing of the nature of the variations or violations and the required corrective actions.

(Ord. No. 2011.01, § 1, 1-11-11)